Phase
One: COMPLETED (May 19 - 27)*
Eastbound
over I-5 Interchange
 |
Suggested
Alternate Routes:
I-5 South to Exit 191
Centennial Blvd.
Harlow Road
Franklin Blvd.
Beltline-Gateway- Pioneer Pky. |
Closure
Map with Narrative PDF
Detail
Map PDF | GIF
How
Traffic Will Be Affected:
On
I-105 (east toward Springfield from Eugene)
- Eastbound
traffic on I-105 will not be able to merge north
onto I-5 toward Portland
- Eastbound
traffic headed toward Springfield on I-105 will not
be able to drive the I-5 overpass into Springfield
- Eastbound
traffic will be routed via Roseburg Exit/Southbound
I-5. Traffic can take Exit 191 (Glenwood), cross
the freeway, and enter northbound I-5.
- Both
lanes of westbound travel will be open, but will
experience delay
From
Springfield (Hwy 126/I-5 interchange - near Gateway)
- West,
south, and northbound traffic will be able to use
all facilities
From I-5 (north-south)
- Southbound
traffic on I-5 will not be able to take the eastbound
Springfield exit at I-105/Hwy 126. Continue south
to Exit 191.
- Southbound
traffic on I-5 will be able to take the westbound
Eugene exit at I-105
- Northbound
traffic on I-5 will be able to take the eastbound
Springfield exit at I-105/Hwy 126 and westbound exit
- All
lanes of both north and southbound I-5 traffic will
be open, but expect increased congestion

Aerial View of Closure Area |
|
*
ODOT and the contractor work closely
to best estimate the dates that
closures will happen, however,
due to the nature of construction,
these dates may change depending
on factors such as weather and
construction delay. The most current
information on I-105 closures will
be posted on a weekly basis. Please
check back regularly.