Franklin Blvd. (OR126B & McVay Hwy: Mississippi Ave – UPRR Tracks (Phase 1))

Construction Update - Week of Mar 17, 2017

Utility work will shift to the intersection of Franklin Blvd. and McVay Hwy; the work is anticipated to occur between 6 pm to 7 am through mid-April. The utility work will require the need for lane closures and detours, as crews access wires and pipes that are below the driving surface of McVay Hwy. Please expect travel delays and detours.

 

This is another exciting step forward in the construction of the New Franklin Blvd. We appreciate your patience as crews make their way passed your home or business. All businesses will remain open and “Business Open” signs will be placed at access point(s) by utility crews while the work is happening.

 

For more information, visit newfranklinblvd.org

 

Questions? Email info@newfranklinblvd.org and we will get back to you promptly.

 

To receive periodic project updates send an email to info@newfranklinblvd.org and include your name.

Completed: No
MTIP: 10 Construction Year: 2017
Jurisdiction: City of Springfield Mode: Road
Bike
Pedestrian
Description:

Construction of the first phase of Franklin Blvd improvements is underway spring 2017 through fall 2018. The contractor for the project is Wildish Construction Company.

  • No residences will be displaced by the road design and construction.
  • Improvements will make it safer for pedestrians and bicyclists to travel to travel in the Glenwood area.
  • The vision for Glenwood is a vibrant Springfield neighborhood, promoting access to the river, and opportunities for employment, housing and recreation.

FranklinJapser2

Rendering of New Franklin Blvd

Image 3

Franklin Blvd will remain open with turn restrictions. Detours and business and residential access will be provided during construction.

Map 4

Business Access During Construction? Yes
Road Closure:

Franklin Blvd will remain open with turn restrictions. Detours and business and residential access will be provided during construction.

Timeline:

Construction underway spring 2017 and is expected to go through fall 2018.

Traffic Impacts:

Expect Delays.

Work Schedule:

Too be determined.

Funding:

STIP, STP-U, and City funding.

Contact: Kristi Krueger
Project Notes:

More information available at www.newfranklinblvd.org

To receive periodic project updates send an email to info@newfranklinblvd.org and include your name.

Map 5

 

Short Description:

Construction will include grading, drainage, paving, signing, lighting, roundabouts, sidewalks, and bike facilities on Franklin Blvd in Glenwood from Mississippi to McVay Hwy.

 