OR 36 Mapleton – Junction City Highway

Construction Update - Week of Sep 18, 2017

OR 36: Mapleton-Greenleaf Chip Seal/Greenleaf-Blachly Paving Project

Remarks: Projects are restoring the existing OR 36 highway. Work is being done Monday –Friday, 6 a.m. to 5 p.m. Between Mapleton and Greenleaf, the chip seal began August 28. The Greenleaf – Blachly overlay paving project will begin paving on September 5. Travelers should expect up to 30 minute delays, with flaggers and pilot car. The two projects are scheduled to be complete by the end of September.

 

Access for pedestrians, including those with disabilities, will be available and identified through or around the work zones .For updates on traffic, go to www.TripCheck.com or call 511.

Information is available in alternative formats upon request. Please call Angela Beers Seydel at 541-726-2442 or call statewide relay at 711.

Completed: No
Jurisdiction: Oregon Dept. of Transportation (ODOT) Mode: Road
Description:

ODOT is paving OR 36 between Blachly to Greenleaf Creek, milepost 29.85 to 21.55

Business Access During Construction? Yes
Traffic Impacts:

The project will be complete by Fall 2017

Work Schedule:

Monday through Friday, day work

Funding:

ODOT Maintenance and Operations budget